Moglicë dam construction activities nearing completion
Moglicë dam construction activities achieve a major milestone with the completion of the construction of its asphalt core
On 23.02.2019 was completed the construction of the asphalt core of the Moglicë dam, a major milestone for the Moglicë HPP project.
The approx. 160 m high dam is an asphalt-core rock-filled structure and will be one the highest of its kind in the world.
The remaining works for completion of Moglicë dam are planned to be completed soon. Good progress is also achieved in the activities for the installation on remaining equipment at the Moglicë powerhouse.
These follow the completion in 2018 of approx. 17 km of tunnels for the Moglicë HPP project.
Moglicë HPP started its construction in 2015 and is planned to start operation in 2019.